|
Roads, bridges
construction work on Yangon-Kyaukpyu Highway Project inspected

Yangon, 19 Sept - Member of the
State Peace and Development Council Lt-Gen Khin Maung Than of the Ministry of
Defence, accompanied by Rakhine State Peace and Development Council Chairman
Commander of the Western Command Maj-Gen Maung Maung Oo and officials, on 16
September inspected building and maintenance of Taungup-Maei Road Section of the
Yangon-Kyaukpyu Highways Construction Project in the rainy season in Rakhine
State.
Next, Lt-Gen Khin Maung Than and
party arrived at Lahmumaw village station hospital in Taungup Township. At the
hospital, Lt-Gen Khin Maung Than urged the officials to make on field trips to
disseminate knowledge on health. He inspected medical stores, and medical room.
Lt-Gen Khin Maung Than and party
proceeded to Maei-Minkyaung road section of Yangon-Kyaukpyu Highway Project. At
the briefing hall, Deputy Superintending Engineer U Than Nyunt of Public Works
reported on progress of Maei-Minkyaung Road Section and tasks being carried out.
Later, Lt-Gen Khin Maung Than and party inspected building of road at milepost
No 8/1 and at Maei-Minkyaung-Painnetaung road section with the use of geotextile
technique. Afterwards, Lt-Gen Khin Maung Than and party arrived at Londawpauk
Bridge construction in An Township and discussed with officials on timely
completion of work meeting the set-standard and attended to the needs. Next,
Lt-Gen Khin Maung Than and party inspected the project site.
They also inspected Thanthamagyi
Bridge Construction Project in Yanbye Township.
Thanthamagyi Bridge will be 552.4
feet long. The bridge will have 24 feet wide motor road and three feet wide
pedestrian ways on both sides. Its clearance will be 111 feet wide and six feet
high. The bridge is being built of iron frame and reinforced concrete. The
construction task was completed by 85 per cent. Efforts are being made for
completion of the bridge at the end of October.
Afterwards, Lt-Gen Khin Maung
Than and party arrived at the construction site of Minkyaung Creek Bridge
Project in Yanbye Township. Senior Engineer U Tin Soe reported on preparations
for installation of 60 metres long steel frame and construction of No 6 pier.
Lt-Gen Khin Maung Than gave
instructions on efforts to be made for installing the steel frame and building
the pier, worksite safety and supervision to be made for timely completion of
the tasks meeting the set standard. He inspected the construction site.

Minkyaung Creek Bridge built of
iron frame and reinforced concrete will be 2,704.2 feet long. The bridge will
have 24 feet wide motor road and three feet wide pedestrian ways on both sides.
Its clearance is 171 feet wide and 38 feet high. The project has been
implemented by 80 per cent. The plan is under way for completion of the bridge
at the end of December.
Next, Lt-Gen Khin Maung Than
presented school stationery for students of Affiliated Basic Education Primary
School at the project site.
On arrival at the briefing hall
of Wamphaik Bridge, Lt-Gen Khin Maung Than gave necessary instructions and
attended to the needs.
At the site of Thazintanpauk
Bridge Project in Yanbye Township, Assistant Engineer U Aung Thein of Public
Works submitted reports on completion of No 6 pier, progress in building No 5
and No 4 piers. Lt-Gen Khin Maung Than fulfilled the requirements and inspected
the construction site.
Afterwards, they proceeded to
Thanthamagyi Bridge Construction Project in Yanbye Township. Lt-Gen Khin Maung
Than heard reports on construction of No 2 approach structure and bored pile and
progress of tasks and attended to the needs.
In the evening, they arrived back
at the site of Thanthamagyi Bridge Project and inspected the site.
Out of 14 bridges which are 180
feet and above long on Taungup-Maei-Kyaukpyu section of Yangon-Kyaukpyu
Highways, eight bridges have been completed. So, efforts are being made for
opening of the remaining six bridges as soon as possible.
Next, Lt-Gen Khin Maung Than and
party arrived back in Maei in the evening.

|